Whether you are doing a full stripout or a targeted defit, the process follows the same sequence.
Step 1: Lease Review and Scope Assessment
Before anything happens on site, the make good clause needs to be read carefully. This defines your legal obligations. A thorough scope assessment considers the original base building condition, what was installed during the tenancy, any landlord-approved variations, and the current condition of surfaces and services.
Step 2: Planning, Permits, and Approvals
Your contractor prepares a project plan covering trade coordination, access requirements, and waste management. Depending on scope and state, commercial demolition may require building permits. For buildings constructed before the mid-1980s, a licensed asbestos assessment is legally required before any demolition begins.
Step 3: Services Disconnection
All building services connected to the fitout must be safely isolated before demolition starts. This covers electrical circuits and data cabling, fitout-specific plumbing, supplementary HVAC, and communications infrastructure. Services disconnection must be carried out by licensed tradespeople and coordinated with building management.
Step 4: Fitout Demolition and Removal
The core of the stripout. Partition removal, suspended ceiling removal, raised floor lifting, joinery and built-ins, floor coverings, and tenant signage are all addressed here. Materials are sorted on site for disposal, recycling, or salvage.
Step 5: Surface Repairs and Reinstatement
Once the fitout is out, anchor points, penetrations, and surface damage are patched and made good. Base building services are reinstated to their original configuration where required by the lease.
Step 6: Painting
Most commercial leases require walls and ceilings to be repainted in a neutral colour before handover. Surface preparation, priming, and painting in the base building colour specification are completed at this stage.
Step 7: Final Clean
A professional end-of-lease clean covers carpet shampooing or hard floor polishing, all glass and windows, surfaces, skirting boards, door frames, and complete waste removal from site.
Step 8: Landlord Inspection and Sign-Off
Your make good contractor coordinates a final inspection with the landlord. Any defects or incomplete items are addressed promptly before formal sign-off discharges your lease obligation.