Lawrence & Hanson | Warehouse Make Good & Demolition
Scroll to explore
CLIENT
Lawrence & Hanson
LOCATION
Knoxfield, Victoria
PROJECT TYPE
End-of-Lease Make Good | Warehouse Demolition | Strip Out | Site Decommissioning
TRADES COORDINATED
Racking | Demolition | Core Drilling | Electrical | Fire Services | Painting | Cleaning
INDUSTRY
Retail & Warehousing
AREA COMPLETED
15,878
SQM
PROJECT DURATION
3 Months
December 2025
to
March 2026
PROJECT OVERVIEW
Lawrence & Hanson engaged National Make Good Solutions (NMGS) to deliver a comprehensive end-of-lease make good and warehouse reinstatement project at their Knoxfield facility in Victoria.
With the lease coming to an end, the objective was to return the 15,878sqm site to a compliant handover condition in accordance with landlord requirements. The project involved extensive demolition, strip-out works, service removals, waste management, and make good reinstatement works, all while coordinating multiple specialist trades within a tight delivery timeframe.
NMGS provided a complete turnkey solution, ensuring the site was restored efficiently and ready for final handover without unnecessary delays or disruption.
Delivering a large-scale warehouse make good project within an active industrial environment presented several challenges.
Key project constraints included:
To overcome these challenges, NMGS implemented a staged delivery program supported by ongoing communication with the client and proactive project management.
SCOPE OF WORK
Warehouse demolition works
Internal strip-out works
End-of-lease make good works
Removal of redundant services
Electrical service removals
Commercial cleaning
Fire service removals
Waste removal and recycling management
Racking removal coordination
Core drilling works
Painting and reinstatement works
Project management and trade coordination
The scope was specifically designed to satisfy landlord reinstatement requirements while minimising operational disruption during the client’s relocation process.
PROJECT DELIVERY
The project required careful planning due to ongoing site activity and the need to coordinate multiple contractors across a large warehouse footprint.
NMGS ensured successful delivery through:
Staged demolition and make good works
Traffic Management Plans to control vehicle and pedestrian movements
Close coordination between specialist trades
Regular communication with the client throughout site vacation activities
Exclusion zones to maintain safety during demolition works
Proactive scheduling to maintain project momentum
This structured approach enabled the project team to maintain productivity while keeping the site safe and operational.
RESULTS & OUTCOMES
The client benefited from a seamless end-of-lease handover process, reducing project complexity and providing confidence that all make good obligations had been met.
Zena Issa
Property Manager, Dexus
Why
NMGS?
This project demonstrates NMGS’s capability to deliver large-scale warehouse make good, demolition, and end-of-lease reinstatement projects across Victoria.
Our team provided:
End-to-end project management
Clear communication throughout delivery
Effective coordination of multiple trades
Safe demolition and strip-out practices
On-time completion against strict lease obligations
A single-contractor solution for warehouse make good and site reinstatement
Whether you’re relocating, vacating a facility, or preparing a commercial property for handover, NMGS delivers efficient and compliant make good solutions across Melbourne and Victoria.
KEY PROJECT METRICS
Site Area
15,878 SQM
Project Duration
3 Months
Location
Knoxfield, VIC
Project Type
End-of-Lease Make Good
Trades Coordinated
6+ Specialist Trades
Waste Recycled
10%
Site Status
Live Operational Environment
Delivery Method
Staged Works Program